Отчет по изпълнението на проекта
The project’s achievements as per First Progress Report can be summarized as follows:
WP 1 Project management and coordination – horizontal
- A Project Manager has been hired for the project
- Both partners are in a process obtaining advance payment and are preparing the documents required by the Project Application Guidelines
WP 2 Building investment
Responsible partner: LB Smart Trip Ltd.
- All construction-related documents have been collected
- Construction work in Shiroka Laka has been started
WP 3 Investment in transport vehicle
Responsible partner: SP Sailing Single Member P.C.
- The PB is in a process of researching available on the market potential boat manufacturers.
- After the contract is signed, the boat will be manufactured within a maximum of 1 (one) year.
WP4 Joint product development
Responsible partner: PB with the active engagement of the LB
- ToRs for the booking platform and the website are in the process of development.
WP 5 Marketing activities
Responsible partner: PB with the active engagement of the LB
- The ToR for selecting the subcontractor for marketing activities is under development.
WP 6 Information and Publicity – horizontal
Responsible partner: LB with the active involvement of the PB
- Both partners have started to develop a Communication & visibility plan to determine the milestones, timeline, resources, target groups and channels to be used.
- The start of the project was announced on the website of the PB – https://spsailing.com/interreg-funding
- Time of the first press-conference to present the project initiative to the general public will be September 2021.
- The website envisaged to be developed by the project will serve both the I&P actions and the commercial platform as a front-end. As reported above under WP 4, both partners have discussed the functionality of the website (front-end) and the requirements for a developer and ToR for the website is under development. Some preliminary meetings have been organized with potential developers.
- The social media profiles in LinkedIn, FB and Instagram will also be used to inform and promote the project. As reported above under WP5, the PPs are in a process of selecting a subcontractor.